HUD

AMS and the Department of Housing and Urban Development (HUD) - Field Services

WINTERIZATION

SCHEDULE FOR ALL STATES IS OCTOBER 1 – MARCH 31

*This is subject to the requirements of Mortgagee Letters 2002-10, 2003-05 or any subsequent policy directives.


EXCEPT FOR THE LOCAL VARIATION FOR THE STATES LISTED BELOW

 


Illinois/Indiana

Winterize as deemed necessary by HUD.  Utilities are to remain off unless required to operate a sump pump.


Caribbean

Do not winterize.

Florida

The water supply should be shut off at the curb.  Notify utility companies to cancel all services.  Do not drain the water heater or water lines.  Do not winterize.

Jacksonville Florida ONLY

Winterize from September 1 through April 30 from Jacksonville north to the Georgia line.  However, heat will remain in shut down mode.  Utilities are to remain off unless required to operate a sump pump.